目 录
第一章:编制依据及说明·········································4
第一节、施工组织设计编制说明·····························4
第二节、编制依据·········································5
第二章:工程概况··············································6
第一节、工程特点·········································6
第二节、工程概况·········································7
第三章:工程施工管理目标······································8
第四章:施工组织管理方案······································8
第一节、项目部管理人员调配管理方案······················8
第二节、项目经理部管理布置计划··························9
第三节、劳动力配备计划··································9
第四节、项目部管理制度的建立····························10
第五节、对专业施工班组的管理设想························11
第五章:施工现场平面布置······································11
第一节、施工现场平面布置原则····························11
第二节、平面布置设想及要求······························12
第三节、施工现场总平面布置图····························13
第六章、施工机械、材料及劳动力计划····························14
第一节、投入本工程的主要施工机械·······················14
第二节、投入本工程的主要材料···························14
第三节、劳动力组织与安排·······························15
第七章:主要分部分项工程的施工方法····························15
第一节、施工顺序·······································15
第二节、施工测量·······································16
第三节、土方、基础工程·································19
第四节、钢筋工程·······································21
第五节、模板工程·······································28
第六节、砼工程·········································30
第七节、砌体工程·······································33
第八节、脚手架工程·····································36
第九节、楼地面工程·····································39
第十节、屋面工程·······································42
第十一节、门窗工程···································44
第十二节、装饰工程···································47
第十三节、给排水工程··································53
第十四节、电气照明工程································59
第十五节、其它工程施工方法····························60
第八章:确保工期的技术组织措施······························63
第一节、施工进度计划··································64
第二节、施工进度计划完成的可行性分析··················64
第三节、工程履约的资源保证措施························65
第四节、施工进度计划管理与工期保证措施················66
第九章:确保工程质量的技术组织措施··························68
第一节、质量目标······································68
第二节、质量保证体系··································68
第三节、质量保证及技术措施·····························70
第十章:确保安全生产的技术组织措施···························79
第一节、安全生产目标···································79
第二节、安全生产管理体系·······························79
第三节、安全生产技术措施·······························80
第十一章:确保文明施工的技术组织措施·························102
第一节、文明施工目标··································102
第二节、文明施工规划及管理制度························102
第三节、文明施工的现场管理措施························103
第四节、施工现场布置要求······························108
第五节、文明施工保证措施······························110
第十二章:季节性施工措施·····································111
第十三章:工程成品保护措施···································112
第十四章:工程保修与回访·····································115
第十五章:工程技术资料管理···································116
附:图表
总平面施工布置图
施工进度计划横道图
拟投入的主要机械设备表
劳动力安排计划表
第一章、编制说明及依据
第一节 施工组织设计编制说明
一、本施工组织设计为我公司递交的湖北长城实业有限公司锦绣龙城二标段工程(4栋、8栋、11栋楼)投标文件之技术性文件,重点阐述了我公司对本工程施工管理中的有关设想、部署及主要采用的技术保障措施。
二、我们完全接受招标文件提出的有关本工程施工质量、施工进度、安全文明施工等一切要求,并落实各项施工方案格技术措施。
三、通过认真学习和研究了该工程的招标文件、有关图纸、答疑资料,并数次勘察了施工现场,在分析了各种影响施工的因素和本工程承包的特点、难点后,我们有充分的信心,在工程安全施工前提下,保证以高质量、高速度全面完成本工程招标文件规定的承包范围全部任务。
四、一旦有幸中标我们将全力以赴,尽快做好施工前期准备和施工现场生产设施的总体规划布置工作。发挥我公司管理优势,建立完善的项目管理组织机构,落实严格的责任制,实施在建设、监理单位的领导和监督管理下的项目总承包管理制度。通过对劳动力、机械设备、材料、技术、方法和信息的优化配置,实现工期、质量、安全社会信誉的预期目标效果。
五、施工中将严格按照招标文件所附施工技术规范标准和湖北省有关的质量规定进行施工,在本工程施工中实行创优工程质量目标管理,确保本工程质量达到武汉市优质工程。
六、我公司将建立严格的质量保证体系,加强施工质量验收制度,绝不违章施工,绝不使用不合格材料,并诚恳地接受各级质量监督部门的监督直至工程竣工验收。
七、为了确保安全生产,我公司将安排专职安