温州市瓯海大道西段快速路工程Ⅲ标












编制:                    
审核:                  

浙江奔腾建设工程有限公司
   温州市瓯海大道西段快速路工程Ⅲ标项目部
2010年5月7日

目  录
一、工程概况··········································3
1、深基坑概况·············································3
2、地质情况···············································4
3、平面位置···············································4
二、编制依据··········································4
三、施工计划··········································5
1、施工时间安排···········································5
2、资源投入情况···········································5
四、工艺方法··········································5
1、总体设想···············································5
2、施工流程···············································6
3、围堰施工···············································6
4、河边桥台开挖支护方法···································6
5、陆地基坑开挖支护方法···································7
6、钢板桩施工·············································7
7、土方开挖···············································8
8、基坑排水···············································9
9、砼结构物施工···········································9
10、钢板桩拔除············································9
五、设计计算··········································9
1、陆地基坑围护计算·······································15
2、河边基坑围护计算······································18
六、安保措施··········································9
1、组织体系建设···········································9
2、沉降监测控制··········································10
3、安全文明措施··········································10
七、其它事项·········································11
1、其它辅助方法··········································11
2、沉木河桥0#台第四幅基坑································11
3、加强与水务部门、地方政府的联系沟通····················12













一、工程概况
1、深基坑概况
瓯海大道西段快速路工程Ш标段全长1061m(k4+124~k5+185),主要为高架桥梁、地面桥和地面道路等,涉及深基坑的承台和桥台位于半塘河、沉木河、中横河等三座桥梁处。
沉木河桥桥台基底标高-1.30m,老河道标高为+1.5m,台后标高为+3.6m。基坑开挖深度4.9m;
中横河桥桥台基底标高-1.30m,老河道标高为+1.4m,台后标高为+3.4m。基坑开挖深度4.7m;
半塘河桥台基底标高-1.30m,位于旱地,台后标高为+5.2m。基坑开挖深度6.5m;
具体位置和开挖深度如下:
部位    结构物平面尺寸    开挖深度    数量    墩位
中横河桥    5.8×32.5    4.8m    1    
    5.8×32.5    4.8m    1    
    5.8×25(7.35)    4.9m    1    
    5.8×25(7.35)    4.4m    1    
沉木河桥    5.8×12.35    4.9m    1    0#台北侧(第一幅)
    5.8×13.70    4.9m    1    0#台北侧(第二幅)
    5.8×12.70    4.6m    1    0#台南侧(第三幅)
    5.8×12.35    4.6m    1    0#台南侧(第四幅)
    5.8×12.35    4.8m    1    3#台北侧(第一幅)
    5.8×13.70    4.8m    1    3#台北侧(第二幅)
    5.8×12.70    4.9m    1    3#台南侧(第三幅)
    5.8×12.35    4.9m    1    3#台南侧(第四幅)
半塘河桥    5.8×7.8    6.5m    2    陆上开挖桥台
    5.8×17.2    6.5m    2    陆上开挖桥台
    5.8×12.7    6.5m    2    陆上开挖桥台
    5.8×12.3    6.5m    2    陆上开挖桥台
主线高架    5.2×8.2    6.5m    2    P62、P63墩承台
    5.2×8.2    6.5m    1    P92墩承台
2、地质情况
根据地质报告分析,地基土主要由浅表部人工回填土、淤泥土组成。在基坑范围内土层性状及右上至下分述为:
(1)杂填土:杂色,松散~中密,力学性质较差。
(2)淤泥:灰色,饱和,流塑,含腐殖质,具高压缩性,下伏于地表粘土层之下,局部直接露于河床,层厚10.9~20.90m,层顶高程0.8~4.2m。粘聚力=10~12kpa,具有高含水量、高压塑性等特性。
因此桥台(承台)地基主要由淤泥组成,广泛分布在场地上,一般厚度在20~35m,该层土具有含水量大、高压缩性、强度底、透水性差等不良工程地质性质。
3、平面位置
     详见附件1
二、编制依据
1、瓯海大道西段快速路工程Ⅲ标段施工图纸、地质勘察报告
2、瓯海大道西段快速路工程Ⅲ标段施工组织设计(总册)
3、《危险性较大的分部分项工程安全管理办法》建质〔2009〕87号文
4、《简明施工计算手册》中国建筑工业出版社(第四版)
5、《城市桥梁工程施工与质量验收规范》CJJ2-2008
6、《钢结构设计规范》GB50017-2003
7、《建筑地基基础设计规范》GB50007-2002

温馨提示

因本站资料资源较多,启用了多个文件服务器,如果浏览器下载较慢,请调用迅雷下载,特别是超过了5M以上的文件!请一定调用迅雷,有时候速度就会飞起哦,如果您的浏览器自动加载了PDF预览,文件太大又卡死,请按下载说明里的把PDF插件关闭了就可以直接下载,不会再预览了!

栏目导航
友情链接: ArchiName筑名导航 孙悟空

网站首页 | 关于我们 | 服务条款 | 广告服务 | 联系我们 | 网站地图 | 免责声明 | WAP
Powered by lubandai.com © 2009-2016 Inc. 桂ICP备16008802号
资源报错、业务联系及其它事务请发邮件与我们联系:admin@lubandai.com