**地下部分钢结构施工方案
一、编制依据 ................................................................................................................................... 3
二、工程概况 ................................................................................................................................... 4
三、施工部署 ................................................................................................................................... 4
3.1 总体部署 ........................................................................................................................... 4
3.2 地下钢柱吊装总平图布置 ............................................................................................... 5
3.3 吊装分区 ........................................................................................................................... 7
3.4 吊装顺序 ......................................................................................................................... 10
3.5 交叉作业流程 ................................................................................................................. 12
3.6 吊车行走通道及构件运输通道 ..................................................................................... 14
四、吊装设备的选择 ..................................................................................................................... 21
4.1 圆管柱吊装设备选择表: ............................................................................................... 21
4.2 Y 型钢柱吊装设备选择表 .............................................................................................. 21
4.3 焊接设备选择表: ........................................................................................................... 21
4.4 用电量计划和复核计算 ................................................................................................. 21
五、劳动力组织计划表 ................................................................................................................. 22
六、工期进度计划安排 ................................................................................................................. 23
七、吊装方法 ................................................................................................................................. 24
7.1 圆管柱吊装 ..................................................................................................................... 24
7.1.1 预埋件安装、钢支架安装及测量保证措施 ..................................................... 24
7.1.1.1 预埋件安装 ..................................................................................................... 24
7.1.1.2 钢支架安装 ..................................................................................................... 25
7.1.2 圆管柱分段 ......................................................................................................... 26
7.1.3 吊车满足吊重要求吊距分析 ............................................................................. 31
7.1.4 首节钢管柱吊装 ................................................................................................. 35
7.1.5 上部钢管柱吊装 ................................................................................................. 40
7.1.7 钢柱测量校正 ..................................................................................................... 42
7.1.8 钢柱安装注意事项 ............................................................................................. 42
7.1.9 钢柱质量的检验标准 ......................................................................................... 43
7.2 Y 型钢柱吊装 .................................................................................................................. 43
7.2.1 Y 型钢柱的分段分节处理和运输 ...................................................................... 43
7.2.2 Y 型钢柱吊装 ...................................................................................................... 47
7.2.3 吊装方法 ............................................................................................................. 49
7.2.4 上部 Y 型钢柱吊装 ............................................................................................. 52
八、现场焊接 ................................................................................................................................. 53
8.1 焊前准备 ......................................................................................................................... 53
8.1.1 人员准备 ............................................................................................................. 53
8.1.2 焊接机具、材料的准备 ..................................................................................... 53
8.1.3 焊接工艺评定 ..................................................................................................... 53
8.2 焊接施工要求 ................................................................................................................. 54
8.2.1 垫板、引弧板,引出板的装配 ......................................................................... 54
8.2.2 焊接环境 ............................................................................................................. 54
8.2.3 焊接工艺参数 ..................................................................................................... 55
8.2.4 焊接顺序 ............................................................................................................. 55
8.2.5 焊缝检验 ............................................................................................................. 57
8.2.6 焊接过程中应注意事项 ..................................................................................... 58
九、安全保证措施 ......................................................................................................................... 58
9.1 安全生产目标 ................................................................................................................. 58
9.2 构件起吊与落位 ............................................................................................................. 59
9.3 吊车安全技术措施 ......................................................................................................... 59
9.4 构件吊装 ......................................................................................................................... 59
9.5 用电安全 ......................................................................................................................... 61
9.6 氧气、乙炔使用安全 ..................................................................................................... 62
9.7 卫生和急救措施 ............................................................................................................. 63
9.8 消防保证措施 ................................................................................................................. 63
9.9 Y 型钢柱焊接安全保证措施 .......................................................................................... 64
9.10 交叉配合施工区域安全保证措施 ............................................................................... 66
十、质量保证体系 ......................................................................................................................... 66
10.1 质量控制措施要点 ....................................................................................................... 67
10.2 钢结构制作质量保证措施要点 ................................................................................... 69
10.2.1 原材料检查 ....................................................................................................... 69
10.2.2 切割、锯割与铣削检验 ................................................................................... 69
10.2.3 制孔检验 ........................................................................................................... 69
10.2.4 装配检验 ........................................................................................................... 69
10.2.5 焊接检验 ........................................................................................................... 69
10.2.6 成品检验 ........................................................................................................... 70
10.2.7 检验记录及相关报告 ....................................................................................... 70
10.3 现场安装质量控制标准 ............................................................................................... 70
10.3.1 主控尺寸 ........................................................................................................... 70
10.3.2 分项控制尺寸 ................................................................................................... 70
10.4 质量控制程序 ............................................................................................................... 71
10.4.1 钢结构安装质量控制程序 ............................................................................... 72
10.4.2 焊接质量控制 ................................................................................................... 73
一一一一、、、、编制依据 编制依据
(1) 《建筑工程施工质量验收统一标准》 GB50300-2001
(2)《低合金高强度结构钢》 GB/T 1591-94
(3)《碳素结构钢》 GB/T 700-88
(4)《熔化焊用钢丝》 GB/T 14957-1994
(5)《气体保护电弧焊用碳钢低合金钢焊丝》 GB/T 8110-95
(6)《埋弧焊用碳钢焊丝和焊剂》 GB/T 5293
(7)《钢结构设计规范》 GB 50017-2003
(8)《型钢混凝土组合结构技术规程》 JGJ 138-2001
(9) 《建筑钢结构焊接技术规程》 JGJ81-2002
(10)《涂装前钢材表面锈蚀等级和除锈等级》 GB8923--88
(11) 《钢结构工程施工质量验收规范》 GB50205-2001
(12)《建筑机械使用安全技术规范》 JGJ33—2001
(13)铁道第四勘察设计院(2008 年 5 月)《新深圳站车站建筑岩土工程详细勘
察报告》
(14)《建筑设计抗震规范》 GB50011-2001
二二二二、、、、工程概况 工程概况
**工程分为主站房和无站台柱雨棚两部分,建筑总面积 181035 ㎡,房屋建
筑面积 74573 ㎡,总用钢量达 5 万吨。车站分为地面站台层、站台层夹层和高架
候车层共三层。主站房东西长 413m,南北宽 208m,建筑高度 42.795m。无站台
柱雨棚东西长 262.6m,南北宽 130m,建筑高度 18.983m。站房钢结构最大跨度
约 86m,最大悬挑约 65m。下部为钢管砼柱与钢-砼楼板组合梁框架结构,屋盖为
双向双层不规则截面桁架钢结构。
主站房基础部分桩基工程灌注桩 256 根,最大桩径为 2200mm/4300mm;Φ
500mm 预制管桩 260 根;承台及明挖基础共计 352 个,其中最大承台尺寸 11000mm
×11000mm×6650mm。
主站房钢柱分为圆管柱和 Y 型钢柱 2 种,其中圆管柱数量 72 根,单根最长
33.84m,单根最重 48.74T;Y 型钢柱 16 根,下部为箱型柱,截面达 4000mm×
2500mm,每米最重达到 10.5T/m。钢梁最长为 43m,最大截面 H1600mm×2300mm×
60mm×84mm,单根钢梁最重 66T。
主站房屋盖主桁架最大单跨 86m,截面高度