糯扎渡水电站工程施工进度管理与控制
葛培清 ,张耀威 ,于红彬
(1.华能澜沧江水电有限公司糯扎渡水电站工程建管局,云南普洱665625;
2.中国人民武装警察部队水电第一总队,广西南宁 530028)
摘 要:工程实施阶段业主的施工进度管理与控制是工程建设管理的重要组成部分,本文从业主的角
度出发,阐述了施工进度管理办法与宏观控制所采取的措施及应注意的相关问题。所得结论可供相关
研究人员参考。
关键词:糯扎渡水电站;施工管理;进度控制;关键线路
中图分类号:TV544(274) 文献标识码:B 文章编号:1000—0860(2014)03—0005—04
M anagement and control from owner of Nuozhadu Hydropower Station on construction progress
GE Peiqing ,ZHANG Yaowei ,YU Hongbin
(1.Construction Administration of Nuozhadu Hydropower Project,Huaneng Lancang River Hydropower Co.,Ltd.,Puer 665625,
Yunnan,China;2.The No.1 Gener~Team of Armed Police Hydropower Troops,Nanning 530028,Guangxi,China)
Abstract:The engineering implementation stage owner"s construction progress management and control is an important part of
projeet construction management,this article from the perspective of the owner.Th is paper expounds the measures for the man—
agement of the construction progress and macro control and measures taken and the related problems that should be paid atten—
tion.The conclusion is to provide a reference for the related researchers.
Key words:Nuozhadu Hydropower Station;construction management;schedule control;key line
1 工程简介
糯扎渡水电站工程位于云南省思茅市和澜沧县
翠云区交界处的澜沧江下游干流上,属于大(1)型
I等工程,永久性主要水工建筑物为一级建筑物。
工程以发电为主兼有防洪、灌溉、养殖和旅游等综
合利用效益,水库具有多年调节性能。糯扎渡心墙
堆石坝最大坝高261.5 In,地下厂房长418 In,宽
31 In,高81.6 In,是目前国内规模较大的地下厂房
之一;开敞式溢洪道水平总长1 445.18 In,宽
151.5 In,校核泄流量31 318 In /s,泄流功率达到
5 586万kW,最大流速为52 m/s。该工程是澜沧江
中下游河段八个梯级规划的第五级,是“西电东送”
的骨干工程,也是目前云南省内在建的最大水电站。
2 工程建设情况
糯扎渡水电站工程根据各阶段工程建设的特点,
WaterResources andHydropowerEngineering Vo1.45 No.3
将工程建设时期划分为四个阶段,即工程筹建期、工
程准备期、主体工程建设期和工程完建期。工程筹建
期即“四通一平”建设,可研阶段施工总工期目标为
33个月,从2004年3月开始,2006年年底结束。工
程准备期即从导流洞工程开工到大江截流这段时间,
可研阶段施工总工期目标为34个月,从2007年年初
开始至2009年10月底结束。主体工程建设期即从各
主体工程陆续建设到第一台机组发电这段时间,可研
阶段施工总工期目标为66个月,从2009年11月初
开始至2015年4月底结束。工程完建期即从第一台
机组发电到工程建设全部完成这段时间,可研阶段施
工总工期目标为35个月,从2015年5月初开始至
2018年3月底结束。
糯扎渡水电站工程在开始筹建期工程招标、建设
收稿日期:2013-12—23
作者简介:葛培清(1974一),男,山东蓬莱人,高级工程师。
5
学兔兔 www.xuetutu.com