温泉水电站混凝土面板堆石坝在 面板 浇筑完成后 ,对其混凝土裂缝进行 了检查统计,并对裂
缝的成因进行 了分析,且介绍 了裂缝处理措施及效果 ,为类似工程的混凝土裂缝处理提供参考。
关键词 :混凝土面板堆石坝;混凝土面板 ;裂缝成 因;处理措施 ;温泉水电站
中图分类号 :TV641.4(245) 文献标识码 :B 文章编号 :1000—0860(2013)10-0093—03
Cracking causation of concrete face of dam for W enquan Hydropower Station and its treatment measures
ZHANG W ei
(Xinjiang Survey and Design Institute of Water Resources and Hydropower,I~riimqi 830000,Xinjiang,China)
Abstract:After the concrete placement of the face slab of the concrete face rockfill dam for W enquan Hydropower Station,the
inspection and statistics are made on the cracks of the concrete face,and then not only the cracking causation is analyzed,but the
measures for the treatment on the cracks and their effects are alSO described herein;which can provide some references for the
treatment of the concrete cracking for the similar projects concerned.
Key words:concrete face rockfill dam ;concrete face slab; cracking causation;treatment measures;Wenquan Hydropower Sta—
tion
1 工程概况
温泉水电站位于新疆某河 中游马扎尔峡谷内,水
库总库容 :2.07亿 m ,水电站总装机容量为 135 MW,
以发电为主 ,多年平均发电量 7.25亿 kW ·h。工程
等别为 Ⅱ等 ,规模为大 (2)型。主要建筑物包括混凝
土面板堆石坝 、表孔溢洪道 、深孔泄洪洞 、引水发电
系统及地面厂房 。混凝 土面板堆石坝为一级建筑物,
最大坝高 102 In。工程坝址区地震基本烈度为 8度 ,
设防烈度为 8度 。
2 面板混凝土 的施工情 况
面板采用二级配 C30W1 2F300钢筋混凝土 ,单层
双向配筋 ,其竖向配筋率为 0.5%,水平 向配筋率为
0.4%。混凝土 面板 面积 约 27 661 In ,混凝 土方量
12 360 In ,钢筋制安 646 t,表面坡 比 1:1.5,面板
为不等厚结构 ,设 计厚度 由底部 63 cm渐 变至坝顶
W ater Resources and HydropowerEngineeffng Vo1.44 No.10
30 am。面 板 设 计 分 块 共 计 32块 ,斜 长 6.199~
175.813 In,分块宽度分为 12 In和 6 In两种,12 In宽
度 16块 ,6 In宽度 l6块。板间缝 31条 ,其 中受压缝
15条 ,受拉缝 16条。
水泥采用 42.5级 普通 硅酸盐 水泥 ,砂 石骨 料
采用 当地骨料筛分厂生产 的砂石骨料 。粗 骨料 采用
二级配 ,最大粒径为 40 mm,分成 5~20 mm,20~
40 mm。混 凝 土设 计 强 度 等 级 为 C30,抗 渗 等 级
W12,抗冻等级 F300。每方掺 0.9 kg纤维。面板混
凝土配合 比如表 1所列。
2009年 4月 1日坝体开始填筑 ,2009年 l2月26
Et填筑 至 防浪 墙 底部 957 In 高 程。混 凝 土 面板 于
2010年 4月 13日开始浇筑 ,2010年 6月 19日浇筑
完成 。面板混凝土浇筑采用坝顶喂料、溜槽入仓 、平