混凝土梁式桥立面线形的修正方法
傅战工,梅大鹏
(中铁大桥勘测设计院有限公司,湖北武汉430056)
摘 要:由于计算参数、计算理论、计算模型、计算方法与实际条件的差别及施工误差等原因,
混凝土梁式桥施工完成后,实际的桥面线形与设计目标不一致,需通过适当调整调平层或铺装层厚
度修正目标线形,保证立面线形匀顺。匀顺的立面线形为在设计的凸曲线范围内没有凹曲线,反之
亦然。修正方法是测量多个离散点的高程,2个端点的铺装厚度按与接线设计高程一致计算,其余
点的初始高程先按最小铺装层厚度计算,然后用逐点判别凹凸性来调整目标高程,再根据目标高程
计算铺装层厚度,从而使全桥线形凹凸性一致,调整后的调平层和铺装层厚度在合理范围内。调平
层和铺装层施工宜按厚度控制,避免铺装施工过程中高程变化对测量的影响。
关键词:混凝土桥;立面线形;修正;桥梁施工
中图分类号:U448.21 文献标志码:A
M odification M ethod for Vertical Geometric
Shape of Concrete Beam Bridge Deck
FU Zhan—gong,M EI Da—peng
(China Railway Major Bridge Reconnaissance& Design Institute Co.,Ltd.,Wuhan 430056,China)
Abstract:Owing to the differences between the calculation parameters,theory,models and
methods and the actual conditions and also owing to the construction errors,the actual vertical
geometric shape of concrete beam bridge deck may not agree with that of the design target after
the bridge is constructed.To ensure the smoothness of the vertical geometric shape of the deck,
the target geometric shape needs to be modified by appropriately adj usting the leveling layer or
deck surfacing thickness.The smoothness of the vertical geometric shape means that within the
range of the designed convex curve,there should be no concave curve and vice visa.To be specif—
ic。the modification method is used to measure the elevation of a number of discretion points.The
deck surfacing thickness at the two end points is calculated according to the agreement of the
thickness with the designed elevation of route alignment.The initial elevation of the rest of the
points is firstly calculated according to the minimum deck surfacing thickness,the target eleva—
tion is adj usted by identifying the convex and concave point by point,the deck surfacing thickness
is then calculated according to the target elevation and consequently the convex and concave of the
whole bridge are kept agreeable and the adj usted leveling layer or deck surfacing thickness is kept
within the rational range. The construction of the leveling layer or deck surfacing thickness
should be preferably carried out according to the thickness control and the influence of variation
of elevation in the construction process on the measurement should be avoided.
因本站资料资源较多,启用了多个文件服务器,如果浏览器下载较慢,请调用迅雷下载,特别是超过了5M以上的文件!请一定调用迅雷,有时候速度就会飞起哦,如果您的浏览器自动加载了PDF预览,文件太大又卡死,请按下载说明里的把PDF插件关闭了就可以直接下载,不会再预览了!