观音阁水库溢流坝段混凝土裂缝
修补工法探究
孟庆玲
(辽宁省水文水资源勘测局,沈阳 110003)
摘 要:观音阁水库采用化学灌浆与手刮聚脲综合处理250.50m高程水平越冬缝。工法的核心是裂缝内部化学
灌浆、手刮聚脲表面封闭,主要工艺分为抗收缩化学灌浆料内部灌浆和手刮聚脲封闭表面裂缝两项。
关键词:水平越冬缝;化学灌浆;聚氨酯;手刮聚脲;界面剂
中图分类号:TV698.2+3 文献标识码:B 文章编号:1673-8241(2014)11-0004-03
Exploration of Concrete Crack Repair Construction M ethod in Guanyinge
Reservoir Spillway Dam Segment
MENG Qing—ling
(Liaoning Hydrology and Water Resources Survey Bureau,Shenyang 1 1 0003,China)
Abstract:Chemical grouting and hand—scraped polyurea are adopted in Guanyinge Reservoir for comprehensively treating
wintering seam at 250.50m elevation leve1.Cores of construction method include internal chemical grouting in cracks and
surface sealing of hand—scraped polyurea.Main process is divided into internal grouting with anti—shrink chemical grouting
materials and surface crack sealing with hand—scraped polyurea.
Keywords: horizontal wintering seam ;chemical grouting;polyurethane;hand—scraped polyurea;interface agent
观音阁水库工程建设期间形成的250.50m高程水
平越冬缝裂缝比较集中,高水位运行时渗漏、冻胀明
显,其中两个溢流表孔下游面冬季出现了“冰包”。
2013年在主汛前腾空库容短暂时段内,水库管理单
位采用化学灌浆与手刮聚脲综合处理工法,选择溢流
坝段的4个坝段作为试验段实施了修补作业。工法的
核心是裂缝内部化学灌浆、手刮聚脲表面封闭,主要
工艺分为抗收缩化学灌浆料内部灌浆和手刮聚脲封闭
表面裂缝两项。实践证明:工法可行、可靠,处理效
果良好,且施工简便,非常适于高危及不规则裂缝部
4
位使用。
1 工程概况
位于太子河干流上的观音阁水库于1995年l0月
建成,是以城市供水和防洪为主,兼顾灌溉、发电和
养鱼的大(1)型水利枢纽工程。控制流域面积
2795km ,总库容21.68亿m ,碾压式混凝土重力拦河
坝全长1040m,最大坝高82m,正常高水位255.20m
(溢流表孔堰顶)。坝体剖面为“金包银”形式,上
游3m防渗层、下游2.5m保护层和2m基础垫层为常