非断流条件下的大坝钢筋
混凝土防渗墙施工
陈锋.赵泽民
(中国葛洲坝集团第一工程有限公司.湖北宜昌430002)
摘要:为了保证工程按期进行,在地质条件较差的河床上非断流条件下.三江El水电站大坝钢筋混凝土防渗墙施
工采用了传统的冲击钻机造孔成槽,泥浆固壁,抽筒换浆清孔,吊车吊放钢筋笼安装,直升导管法灌注水下混凝土
成墙的施工方法。在非断流条件下进行大坝钢筋混凝土防渗墙施工为主体工程施工争取了宝贵工期. 降低了施工成
本,确保了工程节点工期顺利实现。
关键词:非断流;钢筋混凝土防渗墙;施一I 方法; 汀口水电站
Construction of Reinforced Concrete Cutof W all of Dam on the Condition of NOil Flow CutotT
Chen Feng,Zhao Zemin
(China Gezhouba Group No.1 Engineering Co.,Ltd.,Yichang Hubei 4430021
Abstract:In order to guarantee the project construction on schedule,the reinforced concrete cut—of wall of Sanjiangkou
Hydropower Dam is constructed on the condition of non flow cutoff.The construction methods include slurry drilling method
using traditional drilling ri昏pumping slurry for cleaning,reinforcement cage installation with crane,and concrete injection
with vertical conductor pipe.The construction without flow cutof have great contributions on cost reduction and the achieve—
ment of construction schedule.
Key Words:non flow cutof;reinforced concrete cutof wall;construction method;Sanjiangkou Hydropower Station
中图分类号:TV543.82(274) 文献标识码:B 文章编号:0559—9342(2010)02—0068—03
三江口电站大坝及溢洪道主体_[程施工过程中.
由于上游导流洞迟迟未能打通. 无法正常实现大江
截流.错过了2008年的干卉水期 为了实现按时发电
的工程目标.公司制定了一系列的赶T施丁方案.
其中最为重要的就是在非断流条件下进行大坝钢筋
混凝土防渗墙施工. 为后续大坝填筑及混凝土面板
施工争取了宝贵的时间, 同时也大幅降低了大坝填
筑施工强度.从而降低了施工成本
1 非断流条件下防渗墙施工的基本思路
大坝防渗墙是在非断流条件下进行的. 防渗墙
施工必须分段进行 先进行左岸部分防渗墙施工,
让水流从右岸束窄河床通过,利用上游围堰下游戗
堤预进站束窄河床并减少水流对防渗墙施工平台的
冲刷 左岸防渗墙施工完成后。再将左岸上游罔堰
下游戗堤挖出一个满足枯水期泄流的缺口.使河流改
道从左岸戗堤缺口及左岸预留槽段防渗墙通过.将左
岸防渗墙施工平台清除后即可进行右岸防渗墙施工。
为保护施丁平台免受河水冲刷破坏. 必须在施
工平台上下游两侧不小于5 m 的范围内抛填石渣块
石防护, 碾压密实, 待防渗墙施T 平台中间部分主
要用以粘土为主的混合料进行分层填筑密实碾压后.
再在工作平台上布置钢筋混凝土导墙、铺设枕木及
导轨、浇筑倒浆平台、挖排浆沟、布置泥浆系统、
修筑浇筑运输道路等