堆石混凝土技术在山西省的
推广应用
曹继彦
(水利部山西省水利水电勘测设计研究院, 山西太原030024)
摘要:本文简要总结了堆石混凝土技术在山西省的应用与推广。相关实践证明,堆石混凝土技术可
以提高石料利用率25% ~30% ,节省水泥用量50% 以上,综合成本节省高的可达24% ,不但可以获
得高效的施工速度,还能改善混凝土质量。总之,该技术是一项节能环保、节支增收技术。
关键词:堆石混凝土;技术推广;应用实践;山西省
中图分类号:TV641(225) 文献标识码:B 文章编号:1000—0860(2012)09—0050—03
Technical popularization and application of rock-filled concrete in Shanxi Province
CAO Jiyan
(Shanxi Hydroelectric Investigation and Design Institute of Ministry of Water Resources P R.C.,Taiyuan 030o24,Shanxi,China)
Abstract:The technical popularization and application of rock—filled concrete in Shanxi Province are briefly summarized herein.
The relevant practice shows that the technique of rock—filled concrete can increase the utilization rate of the rock material by 25%
~ 30% and save cement content by above 50% along with the saving of the comprehensive cost up to 24% ;with which not only
hjgh efficient construction speed can be obtained,but the quality of concrete can also be improved.Generally,it is really a tech·
nique of energy—saving and environmental protection with cost—saving and benefit—increase.
Key words:rock—filled concrete;technical popularization;application practice;Shanxi Province
1 山西省堆石混凝土技术应用现状
堆石混凝土技术是近年来被广泛关注的一项施
工技术,因其比传统混凝土节约50% 以上的水泥,
在缩短建设周期、节约投资、简化温控并保障工程
质量等方面凸显的经济环保优势,成为促进水利水
电设计与施工单位节本增效的重要途径。山西省从
2008年开始在一些适用堆石混凝土技术的项目上推
广与应用了堆石混凝土技术,几年来,通过6个项
目的具体实施,深深体会到堆石混凝土技术对水利
工程的快速施工、保障工程质量、解决施工中遇到
的难题,节省项目成本及对当地生态环境的保障所
起的友好作用。在实际工程应用中,各级部门统筹
协调,精心组织、落实,全省已经实施的项目工作
都取得了较好效果。
2007年10月20日清峪水库开工奠基,2008年4
月12日,堆石混凝土技术方案替换原设计的常态混
凝土方案顺利通过山西省水利厅审查,标志着堆石混
凝土技术在山西省首个项目正式进入了实施。之后,
恒山水库堆石混凝土技术加固项目启动。再之后,山
西省相继有了千年水库、三湾水库、围滩水电站等堆
石混凝土项目的相继实施。
2 堆石混凝土技术的性能
堆石混凝土技术,涉及到密实、强度、抗渗、水
化热温升这个体系之间的相互联系,其理论依据主要
有以下几个方面。
2.1 密实性能
堆石混凝土填充试验证明,专用自密实混凝土