预应力混凝土用钢棒滞后断裂原因分析
李伟平
(技术中心)
摘要:检验与分析预应力混凝土用钢棒“滞后断裂”原因:钢棒表面有缺陷,特别是有横向
微裂纹之类的缺陷。钢棒表面横向裂纹的主要原因:热轧高线盘条椭圆度过大或表面有耳子、盘条
表面的局部损伤、拉拔的局部润滑不良。
关键词:预应力钢棒;滞后断裂;热轧高线盘条;表面裂纹;椭圆度;拉拔
Cause Analysis on Lagged Fracture of Steel Bar
f0r Prestressed Concrete
LI W eiping
(Technique Center)
Abstract:The causes 1)f lagged fracture of steel bar for prestressed concrete were tested and analyzed:
there were some defects such as transversal micro cracks on the bar surface.The main causes of transversal
cracks on the bar surface included that the ovality of high speed wire rod was too big or there were some fins and
local damages on the rod SUrf3ce,and local lubrication during drawing was not good.
Key W ords:Steel Bar for Prestressed Concrete; Lagged Fracture; Hot—roiled High Speed Wire Rod;
Surface Crack;Ovality;Draw
1 前言
预应力混凝土用钢棒(下称钢棒)用于水
泥管桩制造,一般由专业的钢棒厂使用专用的
热轧光圆盘条(如30MnSi)经过深加工制成,
2013—10,某钢棒厂用柳钢产 14 mm3OMnSi盘
条加工(1)12.6 mm钢棒,产品收集成卷入库后,
在自然时效1~7 d甚至更长时间里,有部分产
品发生自然脆断,用户称之为“滞后断裂”,钢
棒发生滞后断裂的主要规律: (1)比较集中发
生在某几个炉批号的某些卷号上,发生比例占
5% ~50%; (2)在一盘钢棒之中的断口有一到
数个; (3)脆断多数发生在加工后规格为
12.6 mm钢棒,其它规格的钢棒基本不发生脆
作者:李伟平,大学学历,高级工程师,现主要
从事钢铁产品生产研发工作,科长。
断; (4)断口比较平齐(见图la)。本文针对
滞后断裂这一现象进行了相应分析。
2 检验及其结果
为查找断裂产生的原因,通过调查用户现
场生产工艺,取样分析,分析内容包括化学成
分、力学性能、表面酸洗、金相、扫描电镜检
验、现场对比试验等。
(1)钢棒主要生产工艺过程。以柳钢产
30MnSi热轧高线盘条为原料,钢棒主要生产工
艺流程:高线盘条开卷一除鳞脱皮一矫直一拉
拔1一拉拔2(压槽成型)一高频感应加热1一
淬火一高频感应加热2一回火一冷却一收集成
卷一自然时效一合格品发货。其中原料尺寸为
14.0 mm。拉拔l直径尺寸为 13.1 mm,拉
拔2直径尺寸是 12.6 mm (钢棒成品规格),高